Packaging System Upgrades for Top 100 F&B Chocolate Company

Location: Florence, Kentucky

Duration: 16 Days

Overview

Perry Construction Management led a $1.5 million brownfield project at a sweets plant to upgrade its cookie packaging line. Completed in just 16 days, the project involved demolition of the existing Line 3 packaging system and the rapid installation of modern equipment to increase production speed and efficiency, all while coordinating around active plant operations.

Scope of Work

  • Demolition and removal of existing Line 3 packaging system
  • Installation of new scale deck, Multipond scale, check weigher, and GEA bagger
  • Integration of vibratory and trough conveyors
  • Electrical upgrades to support all new equipment
  • Full system startup and commissioning

Results

PCM completed the project on time and within budget, delivering a high-performance packaging system that improved throughput, minimized downtime, and enhanced operational efficiency. The seamless execution and system integration showcased PCM’s ability to manage fast-track upgrades within active manufacturing environments.

June 11, 2025
Location: Austin, Indiana Duration: Completed in 6 Months
June 11, 2025
Location: Indianapolis, Indiana 
June 11, 2025
Location: Laurel, Maryland Duration: 4 Months
June 11, 2025
Location: Brunswick, Georgia Duration: 3 Months
June 11, 2025
Location: Tracy, California Duration: 1 Year
June 11, 2025
Location: Peterborough, Ontario Duration: 9 months
June 11, 2025
Location: Charlotte, North Carolina
June 11, 2025
Location: Blue Anchor, New Jersey Duration: Ongoing
June 11, 2025
Location: Cincinnati, Ohio Duration: 9 Months
More Posts