Packaging System Upgrades for Top 100 F&B Chocolate Company
Location: Florence, Kentucky
Duration:
16 Days
Overview
Perry Construction Management led a $1.5 million brownfield project at a sweets plant to upgrade its cookie packaging line. Completed in just 16 days, the project involved demolition of the existing Line 3 packaging system and the rapid installation of modern equipment to increase production speed and efficiency, all while coordinating around active plant operations.

Scope of Work
- Demolition and removal of existing Line 3 packaging system
- Installation of new scale deck, Multipond scale, check weigher, and GEA bagger
- Integration of vibratory and trough conveyors
- Electrical upgrades to support all new equipment
- Full system startup and commissioning
Results
PCM completed the project on time and within budget, delivering a high-performance packaging system that improved throughput, minimized downtime, and enhanced operational efficiency. The seamless execution and system integration showcased PCM’s ability to manage fast-track upgrades within active manufacturing environments.