Rack Removal Project
Location: Minooka, Illinois
Duration:
1 Month
Overview
Perry Construction Management executed a $1.8 million rack removal project at a 700,000-square-foot warehouse in Minooka, Illinois. The one-month initiative involved the systematic dismantling of 30-foot-tall storage racks using specialized rigging methods.
PCM prioritized worker safety and structural control while ensuring minimal disruption to warehouse operations.

Scope of Work
- Disassembly of 30-foot-tall racking systems
- Use of specialized rigging equipment for top-down removal
- Strict adherence to high-risk worksite safety protocols
- Onsite coordination among skilled riggers and safety personnel
- Protection of surrounding operations during disassembly
Results
The project was completed on time, on budget, and with zero safety incidents. PCM’s precision planning and safety-first approach ensured the secure removal of all racking structures without disruption to adjacent areas. This effort demonstrated PCM’s capability in executing complex, high-risk warehouse disassembly projects with efficiency and control.